Clave | Descripción del auxiliar o básico | Unidad |
AUX048 | Concreto F´c=150 Kg/cm2 | m3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MAT009 | Cemento | ton | 0.313 | 1738.06 | 544.01 |
MAT012 | Grava 1 1/2″ | m3 | 0.7415 | 121.26 | 89.91 |
MAT011 | Arena | m3 | 0.462 | 114.18 | 52.75 |
MAT106 | Agua | m3 | 0.251 | 30.32 | 7.61 |
Suma de Material | 694.28 | ||||
Costo Directo | 694.28 |