| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ANCLAS DE VARILLA DE | ANCLAS DE VARILLA DE 1" | kg |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REDONDO 3/4" | REDONDO 1" | KG | 1.100000 | $11.00 | $12.10 |
| GAS P/CORTES | GAS P/ CORTES | KG | 0.050000 | $3.96 | $0.20 |
| OXIGENO | OXIGENO | M3 | 0.010000 | $38.50 | $0.39 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.050000 | $31.25 | $1.56 |
| PRIMER INORG. | PRIMER INORGANICO DE ZINC GALVADUR | litro | 0.015000 | $65.00 | $0.98 |
| ROSCA P/ANCLA | ROSCA P/ANCLA | PZA | 0.200000 | $40.00 | $8.00 |
| THINNER | THINNER | LT | 0.020000 | $13.10 | $0.26 |
| Suma de Material | $23.49 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.020284 | $691.36 | $14.02 |
| CUAD OC 11 | CUAD. 1 OF. CARPINTERO O.N. + 1AYTE. | jor | 0.020000 | $691.38 | $13.83 |
| Suma de Mano de Obra | $27.85 | ||||
| Herramienta | |||||
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.015000 | $23.49 | $0.35 |
| Suma de Herramienta | $0.35 | ||||
| Equipo | |||||
| AEQUIPO OXICORTE | EQUIPO DE CORTE OXIGENO-GAS | hora | 0.013880 | $10.10 | $0.14 |
| AAESMERILADORA | ESMERILADORA | hora | 0.028440 | $2.64 | $0.08 |
| AEQUIPO PINTURA | EQUIPO DE PINTURA IPSA | hora | 0.010000 | $13.12 | $0.13 |
| Suma de Equipo | $0.35 | ||||
| Otros | |||||
| SAND BLAST | sand blast a metal blanco | kg | 1.100000 | $3.47 | $3.82 |
| Suma de Otros | $3.82 | ||||
| Costo Directo | $55.86 |