| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| SCT-AUX-11 | Andamio metálicos | dia |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SCT-MAT-AND-04 | Marco metalico 155-0 | pza | 4.000000 | $1.31 | $5.24 |
| SCT-MAT-AND-02 | Cruceta o tijeras and. Atlas 255-07 | pza | 4.000000 | $0.48 | $1.92 |
| SCT-MAT-AND-05 | Cople para andamio | pza | 4.000000 | $0.22 | $0.88 |
| SCT-MAT-AND-01 | Plataforma metálica 2.13 mts td/s-7 | pza | 1.000000 | $5.94 | $5.94 |
| Suma de Material | $13.98 | ||||
| Mano de Obra | |||||
| SCT-CUA-06 | Cuadrilla (1 albañil + 1 ayudante) | Jor | 0.055040 | $968.79 | $53.32 |
| Suma de Mano de Obra | $53.32 | ||||
| Costo Directo | $67.30 |