| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BASICO250 | CONCRETO HIDRAULICO DE F'C=250 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT19 | CEMENTO PORTLAND | TON | 0.400000 | $1,850.00 | $740.00 |
| MAT21 | ARENA INCLUYE ACARREO | M3 | 0.480000 | $68.00 | $32.64 |
| MAT20 | GRAVA LIMPIA PARA CONCRETO INCLUYE ACARREO | M3 | 0.820000 | $145.00 | $118.90 |
| Suma de Material | $891.54 | ||||
| Equipo | |||||
| EQPLAC | PLANTA DE MOVILES DE CONCRETO REIMER 250 HP | hora | 0.500000 | $316.14 | $158.07 |
| Suma de Equipo | $158.07 | ||||
| Otros | |||||
| BASAGUA | AGUA | M3 | 0.240000 | $8.31 | $1.99 |
| BASICOALBAÑIL | CUADRILLA DE ALBAÑIL | JOR | 0.100000 | $996.19 | $99.62 |
| Suma de Otros | $101.61 | ||||
| Costo Directo | $1,151.22 |