| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO F-C=300 H/O | CONCRETO H.O. F'C=300 KG/CM2, R.N. AGR. MAX. 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.449000 | $1,800.00 | $808.20 |
| ARENA. | Arena. | m3 | 0.542000 | $45.00 | $24.39 |
| GRAVA LIMPIA | GRAVA LIMPIA | M3 | 0.662000 | $200.00 | $132.40 |
| AGUA | AGUA | M3 | 0.253000 | $35.00 | $8.86 |
| Suma de Material | $973.85 | ||||
| Mano de Obra | |||||
| CUAD OC 40 | CUAD. 1 OP. DE EQUIPO + 7 PEONES | jor | 0.071429 | $2,326.00 | $166.15 |
| Suma de Mano de Obra | $166.15 | ||||
| Equipo | |||||
| REVOLVEDORA 8 H.P. | Revolvedora Kohler sin operador. | HR | 0.533300 | $65.99 | $35.19 |
| Suma de Equipo | $35.19 | ||||
| Costo Directo | $1,175.19 |