| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMB APAR LOSAS | CIMBRA APARENTE EN LOSAS Y TRABES CON TRIPLAY DE PINO DE 16MM Y MADERA DE PINO DE 3a | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0044-2 | MADERA DE PINO DE 3a. | PT | 4.500000 | $6.20 | $27.90 |
| 0049-3 | TRIPLAY DE PINO DE 16 MM. | M2 | 0.200000 | $56.15 | $11.23 |
| 0133-3 | CLAVO | KG | 0.300000 | $6.90 | $2.07 |
| 1037-5 | DIESEL | LT | 1.000000 | $5.15 | $5.15 |
| Suma de Material | $46.35 | ||||
| Mano de Obra | |||||
| 0003-5 | AYUDANTE | jor | 0.100000 | $178.39 | $17.84 |
| 0009-4 | OFICIAL CARPINTERO | jor | 0.100000 | $297.35 | $29.74 |
| Suma de Mano de Obra | $47.58 | ||||
| Herramienta | |||||
| 0000-0 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $47.58 | $1.43 |
| Suma de Herramienta | $1.43 | ||||
| Costo Directo | $95.36 |