| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 35 | CELOSIA DE CONCRETO EN AZOTEA HACIA CUBOS DE VENTILACION, | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CELOSIA DE CONC | CELOSIA DE CONC | M2 | 1.100000 | $172.50 | $189.75 |
| CELOSIA DE CONC | CELOSIA DE CONC | M2 | 1.100000 | $172.50 | $189.75 |
| AGUA | AGUA | M3 | 0.076500 | $46.00 | $3.52 |
| AGUA | AGUA | M3 | 0.076500 | $46.00 | $3.52 |
| Suma de Material | $386.54 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.200000 | $768.76 | $153.75 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.200000 | $768.76 | $153.75 |
| CUADRILLA NO. 02 | (2 peones) | JOR | 0.083300 | $625.64 | $52.12 |
| CUADRILLA NO. 02 | (2 peones) | JOR | 0.083300 | $625.64 | $52.12 |
| Suma de Mano de Obra | $411.74 | ||||
| Herramienta | |||||
| ANDAMIOS | ANDAMIOS | (%)mo | 0.100000 | $0.00 | $0.00 |
| ANDAMIOS | ANDAMIOS | (%)mo | 0.100000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE. 1:5 | MORTERO CEMENTO-ARENA 1:5 | M3 | 0.050000 | $799.12 | $39.96 |
| MORTERO CEM-ARE. 1:5 | MORTERO CEMENTO-ARENA 1:5 | M3 | 0.050000 | $799.12 | $39.96 |
| Suma de Auxiliar | $79.91 | ||||
| Costo Directo | $878.19 |