| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 100. | CONCRETO DE F'c= 100 KG/CM2. HECHO EN OBRA, T.M.A=19 MM, RESISTENCIA NORMAL | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARENA | ARENA | M3 | 0.550000 | $30.00 | $16.50 |
| AGUA | AGUA(MANEJO) | M3 | 0.250000 | $12.00 | $3.00 |
| GRAVA | GRAVA | M3 | 0.650000 | $140.00 | $91.00 |
| CEMENTOG | CEMENTO GRIS | TON | 0.260000 | $1,565.00 | $406.90 |
| Suma de Material | $517.40 | ||||
| Mano de Obra | |||||
| 1A5P | CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) | jor | 0.083000 | $1,244.69 | $103.31 |
| Suma de Mano de Obra | $103.31 | ||||
| Herramienta | |||||
| % MO1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $103.31 | $3.10 |
| Suma de Herramienta | $3.10 | ||||
| Equipo | |||||
| EQREV | REVOLVEDORA P/CONCRETO DE SACO 8 DE HP | hora | 0.500000 | $53.67 | $26.84 |
| Suma de Equipo | $26.84 | ||||
| Costo Directo | $650.65 |