| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| SCT-AUX-04 | SUMINISTRO, FABRICACION Y MONTAJE DE ESTRUCTURA METALICA MEDIANA A BASE DE PLACA DE ACERO A-36 DE 3/16" (37.35 KG/M2) INCLUYE: MATERIAL, CORTES, DESPERDICIOS, SOLDADURA CON ELECTRODOS E-70, CONSUMO DE ENERGIA ELECTRICA, CONSUMO DE MATERIALES, EQUIPO Y MANO DE OBRA. | kg |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SCT-MAT-ACERO-03 | PLACA DE ACERO A-36 DE 3/16" | kg | 1.080000 | $15.80 | $17.06 |
| 00-0009 | CONSUMOS DE FABRICACION EN ESTRUCTURA METALICA | (%)m | 0.100000 | $17.56 | $1.76 |
| 00-0007 | CONSUMOS DE MONTAJE EN ESTRUCTURA METALICA | (%)m | 0.050000 | $17.56 | $0.88 |
| 00-0011 | FLETE DEL TALLER DE ESTRUCTURAS A LA OBRA | kg | 1.000000 | $0.50 | $0.50 |
| Suma de Material | $20.20 | ||||
| Mano de Obra | |||||
| 02-1510 | CUADRILLA No. 151 (PARA FABRICACION DE ESTRUCTURA METALICA.) | Jor | 0.000920 | $8,581.32 | $7.89 |
| 02-1520 | CUADRILLA No. 152 (PARA MONTAJE DE ESTRUCTURA METALICA) | Jor | 0.000920 | $7,081.68 | $6.52 |
| Suma de Mano de Obra | $14.41 | ||||
| Herramienta | |||||
| SCT-HERR-04 | CONTROL DE CALIDAD | (%)mo | 0.025000 | $14.41 | $0.36 |
| Suma de Herramienta | $0.36 | ||||
| Equipo | |||||
| SCT-EQ-34 | MAQUINA DE SOLDAR ELECTRICA | Hora | 0.013890 | $5.68 | $0.08 |
| SCT-EQ-35 | METALERO | Hora | 0.004440 | $11.42 | $0.05 |
| SCT-EQ-36 | MAQUINA CORTADORA DE PLACA ( TORTUGA) IK 12 | Hora | 0.020000 | $2.85 | $0.06 |
| SCT-EQ-31 | GRUA VIAJERA | Hora | 0.000300 | $20.37 | $0.01 |
| SCT-EQ-29 | GRUA PETTIBONE 25,000 LBS. | Hora | 0.000300 | $1,360.86 | $0.41 |
| Suma de Equipo | $0.61 | ||||
| Costo Directo | $35.58 |