| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA | Cimbra aparente PARA BASE DE EQUIPOS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIAMP110 | cimbra imp 1.22x2.44m 16mm 1c | M2 | 0.333300 | $120.00 | $40.00 |
| MADERA POLIN | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 2.153400 | $6.50 | $14.00 |
| CIMBRA07 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.500900 | $5.61 | $14.03 |
| CIAMP045 | chaflan de 3/4" x 8' | ML | 1.150000 | $2.50 | $2.88 |
| CIAMP055 | duela 3/4" x 4" x 8' | PT | 0.637300 | $4.20 | $2.68 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.304500 | $17.00 | $5.18 |
| ALAMBRE REC | ALAMBRE RECOCIDO | KG | 0.048800 | $14.87 | $0.73 |
| DIESEL | DIESEL | LT | 0.500000 | $4.71 | $2.36 |
| Suma de Material | $81.86 | ||||
| Mano de Obra | |||||
| CUAD OC 07 | CUAD. 1 CARPINTERO DE OBRA NEGRA + 1 AYTE. | JOR | 0.108600 | $1,105.17 | $120.02 |
| Suma de Mano de Obra | $120.02 | ||||
| Costo Directo | $201.88 |