Clave | Descripción del Análisis de Precio Unitario | Unidad |
07-6460 | CASTILLO DE CONCRETO SECCION= 20 X 20 CM, CONCRETO F’C=200 KG/CM2-3/4″, CIMBRA 3 CARAS REFORZADO CON 4 VARILLAS R.N. DE 1/2″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 2.425000 | $12.74 | $30.89 |
0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2″ ) | KG | 4.183200 | $10.43 | $43.63 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.948700 | $12.55 | $11.91 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $18.93 | $2.56 |
0950-05 | DIESEL | LT | 0.600000 | $5.41 | $3.25 |
Suma de Material | $95.10 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.160000 | $756.84 | $121.09 |
Suma de Mano de Obra | $121.09 | ||||
Concepto | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.042000 | $981.58 | $41.23 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.160000 | $22.08 | $3.53 |
Suma de Concepto | $44.76 | ||||
Costo Directo | $260.95 |