| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM COMUN CAD Y CAST | CIMBRA COMUN CADENAS Y CASTILLOS | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA | MADERA DE PINO DE 3ª | PT | 6.860000 | $9.00 | $61.74 |
| ALAMBRE REC#18 | ALAMBRE RECOCIDO CAL 18 | KG | 0.054000 | $17.00 | $0.92 |
| CLAVO | CLAVO | kg | 0.225000 | $15.00 | $3.38 |
| DIESEL | DIESEL | LT | 0.360000 | $6.00 | $2.16 |
| Suma de Material | $68.20 | ||||
| Costo Directo | $68.20 |