| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA APARENTE EN C | CIMBRA APARENTE EN COLUMNAS | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIAMP110 | cimbra imp 1.22x2.44m 16mm 1c | M2 | 0.250000 | $92.14 | $23.04 |
| CIAMP090 | polin de 3 1/2"x3 1/2" regular | PT | 1.850000 | $9.80 | $18.13 |
| CIAMP035 | barrote 1 1/2" x 4" x 8' | PT | 1.450000 | $5.62 | $8.15 |
| CIAMP045 | chaflan de 3/4" x 8' | ML | 1.100000 | $2.00 | $2.20 |
| CIAMP055 | duela 3/4" x 4" x 8' | PT | 0.550000 | $7.52 | $4.14 |
| CIMBRA-02 | CLAVO | Kg. | 0.304500 | $17.10 | $5.21 |
| A4BAR012 | alambre recocido cal. 18 | KG | 0.048800 | $11.54 | $0.56 |
| DIESEL | DESMOLDANTE | Lt | 1.100000 | $6.10 | $6.71 |
| Suma de Material | $68.14 | ||||
| Mano de Obra | |||||
| CUA CARPINTERO 2 | (1 Oficial carpintero de obra negra + 1 ayte.) | JOR | 0.100000 | $733.32 | $73.33 |
| Suma de Mano de Obra | $73.33 | ||||
| Costo Directo | $141.47 |