| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CUAD 04 | CUADRILLA 04 ( CARPINTERO DE OBRA NEGRA + AYUDANTE) | jor |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| EQ SEG 01 | EQUIPO DE SEGURIDAD | JGO | 0.010000 | $310.00 | $3.10 |
| HERR 01 | HERRAMIENTA MENOR | (%)mo | 0.060000 | $700.62 | $42.04 |
| Suma de Material | $45.14 | ||||
| Mano de Obra | |||||
| MO 01 | MAESTRO | jor | 0.015000 | $602.89 | $9.04 |
| MO 02 | CABO | jor | 0.030000 | $435.13 | $13.05 |
| MO 03 | PEON Y/O AYUDANTE | jor | 1.000000 | $243.40 | $243.40 |
| MO 05 | CARPINTERO DE OBRA NEGRA | jor | 1.000000 | $435.13 | $435.13 |
| Suma de Mano de Obra | $700.62 | ||||
| Costo Directo | $745.76 |