| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO F-C=250 H/O | Concreto H.O. F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTOGRISII | CEMENTO GRIS | TON | 0.412000 | $1,586.70 | $653.72 |
| AGREGADO 01 | ARENA | m3 | 0.535000 | $30.00 | $16.05 |
| GRAVA 3/4" | GRAVA 3/4" | M3. | 0.637000 | $180.00 | $114.66 |
| AGREGADO-002 | AGUA ACARREO INTERNO | M3 | 0.243000 | $30.00 | $7.29 |
| Suma de Material | $791.72 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 40 | (1 Operador de equipo +7 Peones) | JOR | 0.060000 | $2,440.93 | $146.46 |
| Suma de Mano de Obra | $146.46 | ||||
| Equipo | |||||
| AREVOLVEDORA | REVOLVEDORA 8 H.P | hora | 5.330000 | $64.33 | $342.88 |
| Suma de Equipo | $342.88 | ||||
| Costo Directo | $1,281.06 |