| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050701 | Muro de contencion en concreto | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.539820 | $115,595.00 | $62,400.49 |
| Suma de Mano de Obra | $62,400.49 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR00 | Vibrador de concreto | dÃa | 0.065020 | $72,672.00 | $4,725.13 |
| OBRAFALSA | Obra falsa (alquiler) | dÃa | 2.000000 | $4,365.00 | $8,730.00 |
| Suma de Equipo | $13,455.13 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 1.100000 | $5,000.00 | $5,500.00 |
| Suma de Auxiliar | $5,500.00 | ||||
| Concepto | |||||
| 050120 | Formaleta muro contencion | m3 | 0.033330 | $2,041,900.00 | $68,056.53 |
| 030104 | Ensayos de cilindros a compresion | un | 0.200000 | $60,406.00 | $12,081.20 |
| 030105 | Prueba de asentamiento | un | 0.200000 | $5,462.00 | $1,092.40 |
| 030102 | Diseño de mezclas de concreto | un | 0.020000 | $507,216.00 | $10,144.32 |
| 050203 | Concreto 3000 psi en obra | m3 | 1.100000 | $294,870.00 | $324,357.00 |
| Suma de Concepto | $415,731.45 | ||||
| Costo Directo | $497,087.07 |