| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BA4 | CONCRETO HECHO EN OBRA, FC'= 150 KG./CM2. T.M.A. 3/4" | M3. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 001-CEMT. | CEMENTO GRIS TIPO 1 EN SACO DE 50 KG. | TON. | 0.327540 | $1,980.00 | $648.45 |
| 0302-30 | GRAVA TRITURADA DE 3/4" | M3 | 0.652700 | $321.87 | $210.08 |
| 0302-20 | ARENA | M3 | 0.538210 | $57.50 | $30.95 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.253200 | $23.00 | $5.82 |
| Suma de Material | $895.30 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADR. No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.066670 | $478.34 | $31.91 |
| Suma de Mano de Obra | $31.91 | ||||
| Equipo | |||||
| 03-4050 | REVOLVEDORA PARA CONCRETO MIPSA-KOHLER R-10 8 H.P. 1 SACO | Hora | 0.533330 | $28.70 | $15.31 |
| Suma de Equipo | $15.31 | ||||
| Costo Directo | $942.52 |