| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BASMAT3/4 | SUMINISTRO Y EXTRACCION DE MATERIAL PETREO PARA BASE Y SUB BASE DE 1 1/2" A FINOS | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SCT-MAT-AGRE-04 | Regalias (material para base) | m3 | 1.000000 | $15.00 | $15.00 |
| Suma de Material | $15.00 | ||||
| Equipo | |||||
| SCT-EQ-25 | TRITURADORA DE CONO NORDBERG-SYMONS DE 150 HP. Y MALLAS MOD.200 | Hora | 0.015000 | $641.40 | $9.62 |
| SCT-EQ-19 | Excavadora 320 (160 hp) Caterpillar | Hora | 0.010000 | $489.89 | $4.90 |
| SCT-EQ-02 | Tractor sobre orugas Mod. 1850K marca Case serie NHA411143 | Hora | 0.007000 | $651.62 | $4.56 |
| SCT-EQ-27 | PLANTA DE LUZ 340-B DIESEL DE 65 HP CATERPILLAR | Hora | 0.022000 | $405.36 | $8.92 |
| SCT-EQ-26 | QUEBRADORA DEQUIJADAS NORDBERG-SYMONS T560 130 HP MOD:2000 | Hora | 0.024490 | $985.77 | $24.14 |
| SCT-EQ-24 | CAMION ARTICULADO MCA. DJB 250 HP MOD:2000 | Hora | 0.008000 | $459.10 | $3.67 |
| Suma de Equipo | $55.81 | ||||
| Costo Directo | $70.81 |