| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ANDAMIO METALICO6MTS | ANDAMIO DE 6 MTS DE ALTURA | DIA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MARCO AND. ATLAS | MARCO METALICA | PZA | 6.000000 | $2.10 | $12.60 |
| TIJERAS AND. ATLAS | TIJERAS AND. ATLAS | PZA | 6.000000 | $0.75 | $4.50 |
| COPLES AND. ATLAS | COPLES AND. ATLAS | PZA | 4.000000 | $0.32 | $1.28 |
| MADERA-5 | TABLON P/ANDAMIO | PZA | 0.050000 | $92.00 | $4.60 |
| Suma de Material | $22.98 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.119400 | $859.49 | $102.62 |
| Suma de Mano de Obra | $102.62 | ||||
| Costo Directo | $125.60 |