| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM.CIM | cimbra comun en losa de cimentacion | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA-6 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 0.155500 | $75.66 | $11.77 |
| MADERA-3 | MADERA DE PINO DE 3A. | PT | 5.200000 | $7.49 | $38.95 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 1.660000 | $2.00 | $3.32 |
| CLAVO (VARIAS MED.) | CLAVO DE ACERO AL CARBON DE 2" A 4" | KG | 0.166200 | $12.15 | $2.02 |
| DIESEL | DIESEL | LITRO | 0.600000 | $4.10 | $2.46 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 18 | KG | 0.500000 | $13.00 | $6.50 |
| SEPARADORES DE 30 CM | SEPARADORES DE 30 CMS. | PZA | 3.000000 | $2.50 | $7.50 |
| Suma de Material | $72.51 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 11 | (1 OFICIAL CARPINTERO DE OBRA NEGRA + 1AYUDANTE) | JOR | 0.129870 | $628.27 | $81.59 |
| Suma de Mano de Obra | $81.59 | ||||
| Costo Directo | $154.11 |