| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO F-C=150 MAT | CONCRETO HECHO EN OBRA F'C=150 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.326000 | $2,128.70 | $693.96 |
| ARENA | ARENA PARA CONSTRUCCION | M3 | 0.536000 | $65.00 | $34.84 |
| GRAVA 3/4" | GRAVA DE 3/4 " | M3 | 0.650000 | $300.00 | $195.00 |
| AGUA | AGUA DE TOMA MUNICIPAL | M3 | 0.263000 | $41.00 | $10.78 |
| Suma de Material | $934.58 | ||||
| Equipo | |||||
| REVOLVED. 1 SACO | REVOLVEDORA DE 1 SACO | HR | 0.533300 | $32.91 | $17.55 |
| VIBRADOR | VIBRADOR PARA CONCRETO | HR | 0.555556 | $70.77 | $39.32 |
| Suma de Equipo | $56.87 | ||||
| Costo Directo | $991.45 |