| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2010 | CIMBRA COMUN EN CONTRATRABES Y TRABES DE LIGA EN CIMENTACION A BASE DE CIMBRAPLAY Y MADERA DE PINO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY | Cimbraplay de 16 mm., hoja de 1.22 x 2.44 mts. | m2 | 0.155500 | $110.00 | $17.11 |
| CHAFLAN | 0 | ML | 1.660000 | $3.00 | $4.98 |
| CLAVO | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.166500 | $16.60 | $2.76 |
| ALAMBRE RECOCI | ALAMBRE RECOCIDO DEL NO. 18 | KG | 0.500000 | $13.80 | $6.90 |
| SEPARADORES | 0 | PZA | 3.000000 | $2.50 | $7.50 |
| DIESEL | DIESEL | LT | 0.600000 | $6.00 | $3.60 |
| MADERA D/PINO 3A | 0 | PT | 5.200000 | $6.00 | $31.20 |
| Suma de Material | $74.05 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Carpintero + 1Ayudante) | JOR | 0.129900 | $859.49 | $111.65 |
| Suma de Mano de Obra | $111.65 | ||||
| Costo Directo | $185.70 |