| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BASI350 | BASICO DE CONCRETO DE F'C=350 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT19 | CEMENTO PORTLAND | TON | 0.560000 | $1,850.00 | $1,036.00 |
| MAT21 | ARENA INCLUYE ACARREO | M3 | 0.540000 | $68.00 | $36.72 |
| MAT20 | GRAVA LIMPIA PARA CONCRETO INCLUYE ACARREO | M3 | 0.900000 | $145.00 | $130.50 |
| Suma de Material | $1,203.22 | ||||
| Equipo | |||||
| EQPLAC | PLANTA DE MOVILES DE CONCRETO REIMER 250 HP | hora | 0.500000 | $316.14 | $158.07 |
| Suma de Equipo | $158.07 | ||||
| Otros | |||||
| BASAGUA | AGUA | M3 | 0.290000 | $8.31 | $2.41 |
| BASICOALBAÑIL | CUADRILLA DE ALBAÑIL | JOR | 0.100000 | $996.19 | $99.62 |
| Suma de Otros | $102.03 | ||||
| Costo Directo | $1,463.32 |