| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 332 | DALA DE DESPLANTE DE 30 X 15 CMS. ARMADO CON 4 VR No 3 Y ESTRIBOS No 2 @ 20 CMS. CONCRETO F'C=200 KG/CM2. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO REF.VAR.DIAM. | ACERO DE REFUERZO | KG | 2.460000 | $8.20 | $20.17 |
| ACERO ALAM | ALAMBRON DE 1/4" | KG | 1.170000 | $10.00 | $11.70 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.069000 | $12.00 | $0.83 |
| CONC.PREMEZ.F-C=200 | CONCRETO PREMEZCLADO F'C= 200 KG/CM2 | M3 | 0.049500 | $991.90 | $49.10 |
| Suma de Material | $81.80 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.142857 | $764.36 | $109.19 |
| Suma de Mano de Obra | $109.19 | ||||
| Auxiliar | |||||
| CIMBRA APARENTE | CIMBRA APARENTE | M2 | 0.600000 | $158.05 | $94.83 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $94.83 | ||||
| Costo Directo | $285.82 |