| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESTRU-METALICA | ESTRUCTURA METALICA A BASE DE ACERO A-36 Y PERFILES ESTRUCTURALES INCLUYE SOLDADURA, DESPERDICIOS, MATERIALES, MANO DE OBRA Y HERRAMIENTA | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-PERFIL-A36-01 | A-36 Y PERFILES ESTRUCTURALES | KG | 1.100000 | $11.60 | $12.76 |
| OC-GALVA | GALVANIZADO EN CALIENTE POR INMERSION | KG | 1.100000 | $7.00 | $7.70 |
| OC-COMBUSTIBLE 08 | Gas p/corte | KG | 0.009000 | $8.70 | $0.08 |
| OC-COMBUSTIBLE-11 | Oxigeno | M3 | 0.013000 | $45.00 | $0.59 |
| OC-SOLD1 | SOLDADURA E 7018 | KG | 0.030000 | $27.80 | $0.83 |
| OC-DISCO ABRASIVO | Disco abrasivo para ranurar | PZA | 0.002200 | $45.00 | $0.10 |
| Suma de Material | $22.06 | ||||
| Mano de Obra | |||||
| OC-CUA19 | CUADRILLA (1 PAILERO + 1 AYUD.) | JOR | 0.001080 | $930.12 | $1.00 |
| OC-CUA20 | CUADRILLA (1 SOLDADOR + 1 AYUD.) | JOR | 0.005000 | $1,046.32 | $5.23 |
| OC-CUA21 | CUADRILLA (1 MONTADOR + 4 AYUD.) | JOR | 0.002000 | $1,973.38 | $3.95 |
| Suma de Mano de Obra | $10.18 | ||||
| Equipo | |||||
| OC-EQUIPO 4 | Equipo de corte de oxi-butano | Hora | 0.013880 | $8.77 | $0.12 |
| OC-EQUIPO 11 | Esmeriladora | Hora | 0.028440 | $9.95 | $0.28 |
| OC-EQUIPO 8 | Soldadora marca Lincoln modelo SAE 300 cap. 300 Amp. | Hora | 0.011440 | $112.15 | $1.28 |
| GRUA DE 20 TON | Grua de 20 toneladas marca Grove | Hora | 0.001940 | $1,319.23 | $2.56 |
| Suma de Equipo | $4.24 | ||||
| Otros | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 0.010000 | $109.65 | $1.10 |
| Suma de Otros | $1.10 | ||||
| Costo Directo | $37.58 |