| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MURETE TRANSICION | MURETE DE CONCRETO PARA ALOJAR TUBERIA CONDUIT PARA TRANSICION AERO-SUBTERRANEA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO VARIOS DIAM | ACERO DEL # 3 ( 3/8") AL # 12 (1 1/2") | KG | 22.000000 | $6.80 | $149.60 |
| ALAMBRE | ALAMBRE RECOCIDO | KG** | 0.660000 | $11.64 | $7.68 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 1.330000 | $77.26 | $102.76 |
| CIMBRA05 | CLAVO (VARIAS MED.) | Kg | 1.500000 | $16.25 | $24.38 |
| CIMBRA-04 | MADERA DE PINO | PT | 4.000000 | $5.62 | $22.48 |
| DIESEL | DIESEL | LT | 2.000000 | $4.64 | $9.28 |
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO CPO-30-RS | M3 | 0.600000 | $730.00 | $438.00 |
| Suma de Material | $754.18 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 1.500000 | $508.88 | $763.32 |
| Suma de Mano de Obra | $763.32 | ||||
| Equipo | |||||
| AMAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 H.P. CONJUNTO CABEZAL DE 14" | HR | 0.911144 | $32.32 | $29.45 |
| Suma de Equipo | $29.45 | ||||
| Costo Directo | $1,546.95 |