| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1 | TRAZO Y NIVELACION | M2. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.009000 | $9.20 | $0.08 |
| 0300-60 | CALHIDRA EN SACO | TON | 0.000100 | $1,050.00 | $0.11 |
| 1501-45 | CARRETE DE HILO DE PLASTICO PARA TRAZO CALIBRE 10 | ROL | 0.002000 | $14.30 | $0.03 |
| Suma de Material | $0.22 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADR. No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.004160 | $478.34 | $1.99 |
| Suma de Mano de Obra | $1.99 | ||||
| Costo Directo | $2.21 |