| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| G-7 | CONCRETO F'C=250KG/CM2 , CON IMPERMEABILIZANTE INTEGRAL, EN CISTERNA, | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 1.030000 | $965.00 | $993.95 |
| IMPERMEABILIZANTE IN | IMPERMEABILIZANTE INTEGRAL INCLUIDO EN EL CONCRETO. | M3 | 1.030000 | $80.00 | $82.40 |
| BOMBA PARA CONCRETO | BOMBA P/CONCRETO | M3 | 0.550000 | $130.00 | $71.50 |
| CURACRETO | CURACRETO | LT | 0.800000 | $18.85 | $15.08 |
| AGUA | AGUA | m3 | 0.060000 | $42.75 | $2.57 |
| Suma de Material | $1,165.50 | ||||
| Mano de Obra | |||||
| CUAD OC 42 | 1 Of: Albañil + 2 Ayud.) | jor | 0.083333 | $1,084.90 | $90.41 |
| OC 18 AYUDANTE | AYUDANTE DE OFICIAL | Jor | 0.071429 | $305.84 | $21.85 |
| Suma de Mano de Obra | $112.25 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR. | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $1,277.75 |