| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4 | COLOCACION DE TABIQUE MARCA SANTA JULIA EN COLOR AZUL DE 20 x 10 x 10 CON MORTERO CEMENTO-ARENA, INCLUYE: MATERIAL Y MANO DE OBRA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.040000 | $30.00 | $1.20 |
| ACERO | ACERO REF.VAR.DIAM. | kg | 7.590000 | $10.55 | $80.07 |
| Suma de Material | $81.27 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.156005 | $783.37 | $122.21 |
| Suma de Mano de Obra | $122.21 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1 : 4 | M3 | 0.023625 | $828.09 | $19.56 |
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.026770 | $898.40 | $24.05 |
| ANDAMIOS 1.50-3.00 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3a USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.060700 | $19.13 | $1.16 |
| Suma de Auxiliar | $44.77 | ||||
| Costo Directo | $248.26 |