| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMENT-15 | SUMINISTRO Y HABILITADO DE ACERO DE REFUERZO No. 5 DIAMETRO 5/8" EN ESTRUCTURA (COLUMNAS, TRABES Y LOSAS) RESISTENCIA NORMAL FY=4200 KG/CM2, INCLUYE: MATERIAL, ACARREO LIBRE A 20 MTS., HERRAMIENTA, TRASLAPES, GANCHOS, DESPERDICIOS, MANO DE OBRA Y DEMAS CARGOS CORRESPONDIENTES | TON |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ACERO-REFUER-04 | VARILLA FY=4200 KG/CM2 NO. 5 ( 5/8" ) | TON | 1.100000 | $8,965.51 | $9,862.06 |
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 20.000000 | $14.00 | $280.00 |
| Suma de Material | $10,142.06 | ||||
| Mano de Obra | |||||
| CUA-CHE-05 | CUADRILLA ( 1 FIERRERO + 1 AYUDANTE ) | JOR | 4.750000 | $997.67 | $4,738.93 |
| Suma de Mano de Obra | $4,738.93 | ||||
| Costo Directo | $14,880.99 |