| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ACABADO-01 | SUMINISTRO Y COLOCACION DE AZULEJO DE CERAMICA DE 20 x 30 CMS.,MOD. ASTRATTO COLOR BLANCO ASENTADO A HUESO CON ADHESIVO BLANCO PREMIER, AMBOS MARCA INTERCERAMIC, LECHADEADO CON CEMENTO BLANCO, INCLUYE: MATERIALES, ACARREOS DE LOS MISMOS, MANO DE OBRA, DESPERDICIOS, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-AGLUT-02 | AGUA POTABLE | m3 | 0.080000 | $12.00 | $0.96 |
| CHE-PISO-04 | AZULEJO MOD. ASTRATTO COLOR BLANCO 20 X 30 | M2 | 1.050000 | $93.97 | $98.67 |
| CHE-AGLUT-05 | CEMENTO BLANCO EN SACO | TON | 0.001500 | $3,275.58 | $4.91 |
| CHE-AGLUT-03 | CEMENTO CREST BLANCO | KG | 5.250000 | $3.27 | $17.17 |
| Suma de Material | $121.71 | ||||
| Mano de Obra | |||||
| CUA-CHE-07 | CUADRILLA ( 1 AZULEJERO + 1 AYUDANTE ) | JOR | 0.126582 | $997.67 | $126.29 |
| Suma de Mano de Obra | $126.29 | ||||
| Equipo | |||||
| CHE-EQUIPO-003 | CORTADORA DE AZULEJO. | HR | 0.110000 | $0.75 | $0.08 |
| Suma de Equipo | $0.08 | ||||
| Auxiliar | |||||
| 03-0680 | LECHADA CEMENTO BLANCO-AGUA | M3 | 0.001500 | $4,400.77 | $6.60 |
| Suma de Auxiliar | $6.60 | ||||
| Costo Directo | $254.68 |