| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBAÑI-08 | BASE PARA LUMINARIA DE EXTERIOR A BASE DE CONCRETO ARMADO DE SECCION PIRAMIDAL CORONA = 0.40 X 0.40 , BASE= 0.80 X 0.80, ALTURA= 0.80, ARMADO CON ACERO FY= 4200 KG/CM 2 DEL No. 3 @ 20 CM EN AMBOS SENTIDOS, CIMBRA DESCIMBRA , CONCRETO F'C=200KG/CM2 A.M. 3/4", INCLUYE: MATERIAL, MANO DE OBRA Y TODO PARA SU CORRECTA EJECUCION. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.021000 | $8,965.51 | $188.28 |
| Suma de Material | $188.28 | ||||
| Mano de Obra | |||||
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 1.250000 | $997.67 | $1,247.09 |
| Suma de Mano de Obra | $1,247.09 | ||||
| Auxiliar | |||||
| CHE-CONCRETO150 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.360000 | $1,026.23 | $369.44 |
| CHE-CIMBRA-MURO | CIMBRA APARENTE EN MURO, INCLUYE: CIMBRADO, DESCIMBRADO, SUMINISTRO, MATERIALES DE CONSUMO, MANO DE OBRA Y TRABAJOS NECESARIOS. | M2 | 4.320000 | $387.33 | $1,673.27 |
| Suma de Auxiliar | $2,042.71 | ||||
| Costo Directo | $3,478.07 |