| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IV.14 | LARGUERO L3 IPR DE SECCION 6" x 4" x 13.4 Kg/ML, INCLUYE MONTAJE, NIVELACION, PLOMEO, SOLDADURA A PLACA BASE CON SOLDADURA E-7018, LIMPIEZA Y REBABEO DE AREA DE SOLDADURA, TRASLAPES, CORTES, ACARREOS DENTRO Y FUERA DE LA OBRA Y TODO LO NECESARIO PARA SU CORRECTA COLOCACION Y TERMINACION | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IPR- 6" X 4" | IPR DE SECCION 6" x 4" x 13.4 Kg/ML | KG | 1.050000 | $12.70 | $13.34 |
| GAS P/ CORTES | GAS PARA CORTE | KG | 0.009000 | $9.50 | $0.09 |
| COMBUSTIBLE-04 | OXIGENO | M3 | 0.010560 | $49.44 | $0.52 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.015000 | $27.81 | $0.42 |
| HBACY110 | Disco abrasivo 12" para concreto | pza | 0.002000 | $141.00 | $0.28 |
| CARDA | CARDA | PZA | 0.000400 | $192.00 | $0.08 |
| FLETES Y MANEJOS | FLETES Y MANIOBRAS | (%)m | 0.037481 | $0.00 | $0.00 |
| Suma de Material | $14.72 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | jor | 0.003070 | $679.88 | $2.09 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | jor | 0.003070 | $679.88 | $2.09 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | jor | 0.001381 | $1,340.79 | $1.85 |
| Suma de Mano de Obra | $6.03 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | Equipo de corte de oxi-acetileno | HR | 0.013880 | $6.05 | $0.08 |
| ESMERILADORA | Esmeriladora | HR | 0.028440 | $2.11 | $0.06 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.011440 | $8.74 | $0.10 |
| GRUA 20 TON | GRUA DE 20 TON | HR | 0.000700 | $577.57 | $0.40 |
| Suma de Equipo | $0.65 | ||||
| Costo Directo | $21.39 |