| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PISOS-01 | PISO DE 10 CM. DE ESPESOR CONCRETO PREMEZCLADO MR-38, ACABADO PULIDO VACIADO CON BOMBA, INCLUYE: TRAZO, NIVELACION, EXCAVACION, CIMBRA, DESCIMBRA, VIBRADO A REGLA VIBRADORA, CURADO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-CONCRETO-021 | CONCRETO PREMEZCLADO MR - 38 | M3 | 0.105000 | $994.84 | $104.46 |
| CHE-CIMBRA-01 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.900000 | $9.85 | $8.87 |
| CHE-CONCRETO-05 | BOMBEO DE CONCRETO | m3 | 0.105000 | $110.00 | $11.55 |
| CHE-PAVIM-01 | BARRA DE ACERO DE 3/4" X 1.00 MT. EN REFUERZO DE JUNTAS | PZA | 1.000000 | $58.50 | $58.50 |
| CHE-ACERO- 6X6/6-6 | MALLA ELECTROSOLDADA 6X6 | M2 | 1.050000 | $20.68 | $21.71 |
| Suma de Material | $205.09 | ||||
| Mano de Obra | |||||
| CUA-CHE-06 | CUADRILLA ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.035000 | $2,779.31 | $97.28 |
| Suma de Mano de Obra | $97.28 | ||||
| Equipo | |||||
| CHE-EQUIPO-028 | REGLA VIBRATORIA | HR | 0.032053 | $171.53 | $5.50 |
| Suma de Equipo | $5.50 | ||||
| Auxiliar | |||||
| CHE-CIMBRA-PISO | CIMBRA EN PISOS DE CONCRETO DE 15 CMS DE ESPESOR INCLUYE CHAFLAN Y PERFORACIONES A CADA 60 CMS PARA PASAJUNTAS | M2 | 1.000000 | $35.35 | $35.35 |
| Suma de Auxiliar | $35.35 | ||||
| Costo Directo | $343.21 |