| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 15-EX | SUMINISTRO, FABRICACION, TRANSPORTE Y MONTAJE DE ESTRUCTURA METALICA DE ANUNCIO ESPECTACULAR, INCLUYE: CONEXIONES, SOLDADURAS CALIDAD RADIGRAFIABLE EN SU CASO, TORNILLERIA CON TORQUES DE ACUERDO A ESPECIFICACIONES, PLANOS DE TALLER, PRIMARIO | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IPR DIF. MEDIDAS | IPR DE DIFERENTES MEDIDAS | KG | 0.200000 | $9.50 | $1.90 |
| LONA AHULADA-A | lona ahulada | m2 | 0.015000 | $170.00 | $2.55 |
| VIGA HP | VIGA HP | KG | 0.509900 | $10.00 | $5.10 |
| PLACA DE ACERO | PLACA 1/4" ACERO | KG | 0.227800 | $11.00 | $2.51 |
| CANAL ESTRUCTURAL | CANAL ESTRUCTURAL | KG | 0.054250 | $9.00 | $0.49 |
| ANGULO DIF. MEDIDAS | ANGULO METALICO | KG | 0.054250 | $10.00 | $0.54 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.009000 | $4.05 | $0.04 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.008500 | $40.00 | $0.34 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.007330 | $30.00 | $0.22 |
| ALAMBRE TUBULAR | ALAMBRE TUBULAR | KG | 0.004000 | $28.00 | $0.11 |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002200 | $75.00 | $0.17 |
| SPOT LABORATORIO | SPOT LABORATORIO | KG | 1.000000 | $0.15 | $0.15 |
| TORNILLERIA | TORNILLERIA | KG | 0.001000 | $60.00 | $0.06 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.021350 | $0.00 | $0.00 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 0.009600 | $47.00 | $0.45 |
| THINER | THINER | LT | 0.076190 | $12.00 | $0.91 |
| Suma de Material | $15.53 | ||||
| Mano de Obra | |||||
| CUAD OC 39 | (1 Of. Pailero + 1 Ayud.) | jor | 0.002500 | $783.30 | $1.96 |
| CUAD OC 37 | (1 of.soldador + 1 ayud.) | jor | 0.002500 | $802.01 | $2.01 |
| CUAD OC 36 | (1Of. Maniobrista + 3 Ayud.) | JOR | 0.001500 | $1,433.06 | $2.15 |
| CUAD OC 18 | (1 Of. Pintor +2 Ayudante). | JOR | 0.001667 | $963.99 | $1.61 |
| Suma de Mano de Obra | $7.72 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.013880 | $0.59 | $0.01 |
| ESMERILADORA | Esmeriladora | HR | 0.021000 | $10.06 | $0.21 |
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.018310 | $31.60 | $0.58 |
| GRUA 20 TON | GRUA DE 20 TON | HR | 0.002300 | $574.57 | $1.32 |
| COMPRESOR AIRE | EQUIPO PARA PINTAR CON ACCESORIOS | HR | 0.035290 | $13.26 | $0.47 |
| Suma de Equipo | $2.59 | ||||
| Concepto | |||||
| 3101-E01 | SUMINISTRO DE ANCLAS DE ACERO A-36 DE HASTA 1" DIAM. x 0.90 M. LONG. Y 0.30 DE PATA, PARA ESTRUCTURA METALICA INCLUYE: ROSCA DE 15 CM., 2 TUERCAS Y RONDANA. | PZA | 0.001000 | $220.00 | $0.22 |
| 3101-E05 | SUMINISTRO, HABILITADO Y MONTAJE DE TORNILLOS DE ALTA RESISTENCIA ASTM A-325 (TENSION CONTROLADA) | PZA | 0.059000 | $24.87 | $1.47 |
| Suma de Concepto | $1.69 | ||||
| Costo Directo | $27.53 |