| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBAÑI-03-1 | CASTILLO DE SECCION 0.20 X 0.20 MT., CONCRETO F'C=200 KG/CM2, AGREGADO MAXIMO 3/4", CIMBRA 2 CARAS, REFORZADA CON 4 VARILLAS DE 3/8", ESTRIBOS DE 1/4" A/C 20 CM., INCLUYE: MATERIAL, MANO DE OBRA, DESPERDICIOS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-CIMBRA-01 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.133300 | $11.40 | $24.32 |
| CHE-CIMBRA-07 | CIMBRAPLAY DE PINO DE 16 MM 1 CARA | HOJA | 0.080000 | $310.00 | $24.80 |
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.002339 | $10,450.00 | $24.44 |
| CHE-ACERO-REFUER-05 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | TON | 0.000843 | $12,000.00 | $10.12 |
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $13.82 | $2.76 |
| CHE-CIMBRA-02 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $16.55 | $2.23 |
| CHE-COMBUST-01 | COMBUSTIBLE DIESEL | LT | 0.240000 | $8.32 | $2.00 |
| Suma de Material | $90.67 | ||||
| Mano de Obra | |||||
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.150000 | $1,006.54 | $150.98 |
| Suma de Mano de Obra | $150.98 | ||||
| Auxiliar | |||||
| CHE-CONCRETO200 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.031500 | $1,213.47 | $38.22 |
| Suma de Auxiliar | $38.22 | ||||
| Costo Directo | $279.88 |