| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OESP-21 | SUMINISTRO Y COLOCACION MATERIALES PARA ALIMENTACION ELECTRICA A REBANADORA DE PAN , ALIMENTACION DESDE EL EDC HASTA EL AREA DE AMASIJO , INCLUYE TRABAJAR ARRIBA DE PLAFOND YA TERMINADO , TUBERIA, CABLES, CAJAS CONEXIONES Y MANO DE OBRA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.G.P.G. 21MM. | TUBO C.G.P.G. 21MM. | ML | 44.500000 | $17.80 | $792.10 |
| CABLE THW CALIBRE 8. | CABLE THW-LS CALIBRE 8 MARCA CONDUMEX | ML | 145.000000 | $6.90 | $1,000.50 |
| CABLE CU DESN.CAL 10 | CABLE CU DESNUDO CALIBRE 10 MARCA CONDUMEX | ML | 54.000000 | $2.90 | $156.60 |
| CONTACTO 10 | CONTACTO TRSIFASICO 220 VOLTS, 3F-4H , 15-30 AMP. CON SEGURO DE MEDIA VUELTA CON TAPA | PZA | 1.000000 | $412.00 | $412.00 |
| CLAVIJA TRIFASICA | PZA | 1.000000 | $466.00 | $466.00 | |
| CONDULET 21 OVAL | LR-LB | PZA | 1.000000 | $58.00 | $58.00 |
| Suma de Material | $2,885.20 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 5.000000 | $775.62 | $3,878.10 |
| Suma de Mano de Obra | $3,878.10 | ||||
| Equipo | |||||
| CARRITO ELEVADOR GEN | GENNY | R/H | 48.000000 | $100.23 | $4,811.04 |
| Suma de Equipo | $4,811.04 | ||||
| Costo Directo | $11,574.34 |