| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 611 | PROTECCIONES EN AREA DE CARRITOS EN EL AREA DEL ESTACIONAMIENTO A BASE DE TUBO GALVANIZADO DE 2" DE DIAMETRO, CED. 40 ALTURA H=0.90m CON CIMENTACION PARA CADA POSTE (16 POSTES EN TOTAL) DE CONCRETO ARMADO DE 0.20M x | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.200000 | $30.00 | $6.00 |
| PERFIL PTR | PERFIL ESTRUCTURAL PTR | KG | 8.000000 | $9.50 | $76.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.100000 | $4.05 | $0.41 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.200000 | $40.00 | $8.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.100000 | $31.25 | $3.13 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 0.100000 | $47.00 | $4.70 |
| THINER | THINER | LT | 0.100000 | $12.00 | $1.20 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 0.160000 | $67.00 | $10.72 |
| Suma de Material | $110.15 | ||||
| Mano de Obra | |||||
| CUAD OC 39 | (1 Of. Pailero + 1 Ayud.) | jor | 0.140000 | $783.30 | $109.66 |
| CUAD OC 18 | (1 Of. Pintor +2 Ayudante). | JOR | 0.050000 | $963.99 | $48.20 |
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.020000 | $763.77 | $15.28 |
| Suma de Mano de Obra | $173.14 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.100000 | $31.60 | $3.16 |
| ESMERILADORA | Esmeriladora | HR | 0.100000 | $10.06 | $1.01 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.100000 | $0.59 | $0.06 |
| Suma de Equipo | $4.23 | ||||
| Costo Directo | $287.51 |