| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4.44.13 | SUMINISTRO E INSTALACIÓN DE CRUZ DE PVC METR-METR 200 X 100 MM C-7 CEM. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0767698 | CRUZ HID METR-ING. C/4C 200-100 MM TC 7 | PZ | 1.000000 | $633.75 | $633.75 |
| 2902026 | ANILLO HID METR. 200 MM (EQK-2902026) | PZ | 2.000000 | $15.94 | $31.88 |
| 2901058 | ANILLO HID ING. 100 MM (EQK-2901058) | PZ | 2.000000 | $4.65 | $9.30 |
| 9700142 | LUBRICANTE REXOLIT LATA500 GRS. | PZ | 0.072000 | $11.55 | $0.83 |
| Suma de Material | $675.76 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.080070 | $749.35 | $60.00 |
| Suma de Mano de Obra | $60.00 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.036750 | $163.91 | $6.02 |
| Suma de Equipo | $6.02 | ||||
| Costo Directo | $741.79 |