| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 6.2.4 | SUMINISTRO E INSTALACIÓN DE TEE PVC DE 4" C-40 CEM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0306103 | T PVC C-40 HID CEM. 100 MM | PZ | 1.000000 | $549.68 | $549.68 |
| 9700130 | LIMPIADOR REXOLIT .500 LTS. | PZ | 0.240000 | $8.82 | $2.12 |
| 9700254 | CEMENTO AGRICOLA 480 ML | PZ | 0.391000 | $24.80 | $9.70 |
| Suma de Material | $561.49 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.016010 | $749.35 | $12.00 |
| Suma de Mano de Obra | $12.00 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.007350 | $163.91 | $1.20 |
| Suma de Equipo | $1.20 | ||||
| Costo Directo | $574.70 |