| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-03. | CADENA DE DESPLANTE DE CIMENTACION DE CONCRETO HIDRAULICO F'C=200KG/CM2 DE 25X20CM, ARMADO CON 4 VARILLAS DEL No.4 Y ESTRIBOS DEL No.3 A CADA 20CM, INCLUYE CIMBRA Y DESCIMBRA ACABADO COMUN, EL PRECIO UNITARIO INCLUYE: MATERIALES, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.077000 | $723.12 | $55.68 |
| ACERO 03 | ACERO DEL # (3/) | KG | 2.670000 | $6.00 | $16.02 |
| ACERO-022 | ALAMBRON | KG | 2.740000 | $6.00 | $16.44 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $5.00 | $6.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.175000 | $80.00 | $14.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.200000 | $10.00 | $2.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.010000 | $10.43 | $0.10 |
| Suma de Material | $111.34 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.222220 | $440.17 | $97.81 |
| Suma de Mano de Obra | $97.81 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.98 | $1.60 |
| Suma de Equipo | $1.60 | ||||
| Costo Directo | $210.76 |