| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| OE-11 | FABRICACI脫N DE TOPES DE 0.12 X 0.20 MTS. X 0.60 MTS. DE LONGITUD, ARMADO CON 4 VAR. DEL #3 Y ESTRIBOS DEL #2 A CADA 20 CMS. PARA AUTOMOVIL EN 脕REA DE ESTACIONAMIENTO A BASE DE CONCRETO F'C=150 KG/CM2., CON DOS MANOS DE PINTURA COLOR AMARILLA, INCLUYE: MATERIAL, MANO DE OBRA, HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | PZA |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-3/8" | ACERO DE 3/8" | TON | 0.001350 | $9,500.00 | $12.83 |
| ACERO-1/4 | ALAMBRON DE 1/4 | KG | 0.850000 | $10.49 | $8.92 |
| ACERO-18 | ALAMBRE RECOCIDO | KG-- | 0.100000 | $12.17 | $1.22 |
| CIMBRA-01 | CIMBRAPLAY 16 MM | M2** | 0.100000 | $80.62 | $8.06 |
| CIMBRA-02 | CLAVO | Kg.-- | 0.250000 | $13.54 | $3.39 |
| Suma de Material | $34.41 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Pe贸n) | JOR | 0.200000 | $668.45 | $133.69 |
| Suma de Mano de Obra | $133.69 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 KG | CONCRETO DE F'C= 150 KG/CM2 | M3 | 0.020000 | $713.67 | $14.27 |
| Suma de Auxiliar | $14.27 | ||||
| Costo Directo | $182.37 |