| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 135 | DE 40 X 100 CM, (D-431-01-4-4695) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.440000 | $1,568.24 | $690.03 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.440000 | $134.17 | $59.03 |
| CIMBRA COMUN LOSAS | CIMBRA COMUN EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 3.080000 | $176.10 | $542.39 |
| ACERO ESTRUC. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.008624 | $9,398.41 | $81.05 |
| ACERO ESTRUC. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.017600 | $9,131.61 | $160.72 |
| Suma de Auxiliar | $1,533.22 | ||||
| Costo Directo | $1,533.22 |