| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ACA-20 | SUMINISTRO Y COLOCACION DE FORRADO DE COLUMNAS CON PANEL DE TABLARROCA UNA CARA, INCLUYE: MATERIAL, MANO DE OBRA Y HERRAMIENTA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| DUROCK-003 | POSTE METALICO USG 9.20 * 3.05 CAL 22 | ML | 19.200000 | $15.63 | $300.10 |
| DUROCK-006 | CANAL 6.35 CAL. 22 | ML | 3.600000 | $16.00 | $57.60 |
| DUROCK-005 | TORNILLO PARA DUROCK DE 1 1/4" | PZA | 25.000000 | $0.36 | $9.00 |
| DUROCK-007 | TORNILLO METAL METAL | PZA | 15.000000 | $0.60 | $9.00 |
| TABLARROCA 14 | FULMIMNANTEDX-72 | PZA | 7.000000 | $1.50 | $10.50 |
| TABLARROCA 18 | ANCLA HILTI DX-72 | PZA | 7.000000 | $1.90 | $13.30 |
| TABLARROCA-14 | Panel de tablarroca de 13 mm ( 1.22 * 2.44 mts. ) den glass | hoja | 1.500000 | $130.00 | $195.00 |
| TABLARROCA-06 | Perfacinta refuerzo para juntas rollo de 75.00 ml. | rollo | 12.800000 | $21.46 | $274.69 |
| TABLARROCA-07 | Compuesto redimix p/juntas caja de 25 kg | caja | 0.200000 | $114.14 | $22.83 |
| Suma de Material | $892.01 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 97 | (1 Of.Tablaroquero + 1 Ayud.) | Jor | 0.250000 | $803.81 | $200.95 |
| Suma de Mano de Obra | $200.95 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO METALICO | DIA | 0.500000 | $28.26 | $14.13 |
| Suma de Auxiliar | $14.13 | ||||
| Costo Directo | $1,107.09 |