| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBEX-004-DOR-EXT2 | SUMINISTRO Y COLOCACION DE RELLENO FLUIDO EN AZOTEA CON UN ESPESOR DE 15 CMS. DEL EDIFICIO DE DORMITORIOS PARA DAR PENDIENTES REQUERIDAS, INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION Y MANTENIMIENTO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| RELLENO FLUIDO | RELLENO FLUIDO | M3 | 0.156000 | $670.00 | $104.52 |
| RELLENO FLUIDO | RELLENO FLUIDO | M3 | 0.156000 | $670.00 | $104.52 |
| CONCRETO-003 | SERVICIO DE BOMBEO | m3 | 0.156000 | $135.00 | $21.06 |
| CONCRETO-003 | SERVICIO DE BOMBEO | m3 | 0.156000 | $135.00 | $21.06 |
| Suma de Material | $251.16 | ||||
| Mano de Obra | |||||
| 02-1570 | CUADRILLA No. 157 (DE COLOCACION DE CONCRETO) | jor | 0.028571 | $4,247.16 | $121.35 |
| 02-1570 | CUADRILLA No. 157 (DE COLOCACION DE CONCRETO) | jor | 0.028571 | $4,247.16 | $121.35 |
| Suma de Mano de Obra | $242.69 | ||||
| Costo Directo | $493.85 |