| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.11A | CIMBRA AHOGADA EN CIMENTACION CON MADERA DE PINO, INCLUYE:MATERIALES DE CONSUMO, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA-6 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 0.200000 | $92.00 | $18.40 |
| MADERA-3 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 3.900000 | $7.50 | $29.25 |
| CLAVO (VARIAS MED.) | CLAVO DE ACERO AL CARBON DE 2" A 4" | KG | 0.396000 | $17.00 | $6.73 |
| DIESEL | DIESEL | LITRO | 0.500000 | $7.00 | $3.50 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 2.000000 | $2.50 | $5.00 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.140000 | $14.00 | $1.96 |
| ACERO REF 3-8 | ACERO DE REFUERZO MCA.T-A | KG | 1.200000 | $9.50 | $11.40 |
| Suma de Material | $76.24 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 11 | (1 OFICIAL CARPINTERO DE OBRA NEGRA + 1AYUDANTE) | JOR | 0.166700 | $667.01 | $111.19 |
| Suma de Mano de Obra | $111.19 | ||||
| Costo Directo | $187.43 |