| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C-15 | BASE PARA TINACO 1100 LT | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0534-00 | BLOCK DE CONCRETO PESADO DE 20 X 20 X 40 CM HUECO | MILL | 0.006000 | $4,800.00 | $28.80 |
| SEGURIDAD IND. | SEGURIDAD INDUSTRIAL PARA PERSONAL | LOTE | 1.000000 | $2.00 | $2.00 |
| Suma de Material | $30.80 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.515340 | $559.85 | $288.51 |
| Suma de Mano de Obra | $288.51 | ||||
| Auxiliar | |||||
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | M3 | 0.180000 | $768.01 | $138.24 |
| Suma de Auxiliar | $138.24 | ||||
| Costo Directo | $457.55 |