| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ............. | En cabezales, topes, bancos y pantalles | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO CPO-30-RS | M3 | 1.050000 | $730.00 | $766.50 |
| PAVIMENTO-06 | MEMBRANA DE CURADO WRMEADOWS | LT | 0.150000 | $8.89 | $1.33 |
| REVENIMIENTO | REVENIMIENTO PARA BOMBEO | M3 | 1.050000 | $65.00 | $68.25 |
| CONCRETO PRE-02 | SERVICIO DE BOMBEO | M3 | 1.050000 | $115.00 | $120.75 |
| CIMBRA-04 | MADERA DE PINO | PT | 3.000000 | $5.62 | $16.86 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 0.450000 | $77.26 | $34.77 |
| CIMBRA05 | CLAVO (VARIAS MED.) | Kg | 0.020000 | $16.25 | $0.33 |
| DESCUENTO DE ACERO | DESCUENTO DE VOLUMEN DE ACERO CON REFERENCIA AL CONCRETO DE FC=250 KG/CM2 | M3 | -0.014800 | $730.00 | -$10.80 |
| Suma de Material | $997.98 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.150000 | $508.88 | $76.33 |
| Suma de Mano de Obra | $76.33 | ||||
| Equipo | |||||
| AMAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 H.P. CONJUNTO CABEZAL DE 14" | HR | 0.182230 | $32.32 | $5.89 |
| Suma de Equipo | $5.89 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO RENTA POR DIA | DIA | 0.150000 | $56.75 | $8.51 |
| Suma de Auxiliar | $8.51 | ||||
| Costo Directo | $1,088.72 |