| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EC-015 | FABRICACION DE CISTERNA PARA 10.6 M3 DE CAPACIDAD, CON MEDIDAS DE 2.5x2.5x1.70 MTS INCLUYE ESCAVACION, RELLENOS, CONEXIÓN DE LA LINEA DE ALIMENTACION, PRUEBA, LIMPIEZA Y TODOS LOS MATERIALES NECESARIOS PARA SU ELABORACION. | PG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| FESTERGRAL | FESTERGRAL | KG | 6.500000 | $7.06 | $45.89 |
| MARCO/CONTRA 40X60 | CONTRAMARCO 2"X1/4" Y MARCO 1 1/2"X 1/4" 40 X 60 CM. | PZA | 1.000000 | $280.00 | $280.00 |
| CODO DE PVC 4" | CODO DE PVC 4" | PZA | 4.000000 | $7.00 | $28.00 |
| Suma de Material | $353.89 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 4.000000 | $749.36 | $2,997.44 |
| CUADRILLA NO. 01 | CUADRILLA NO. 1 (1 PEON) | Jor | 0.200000 | $287.39 | $57.48 |
| Suma de Mano de Obra | $3,054.92 | ||||
| Auxiliar | |||||
| HAB/ARM ACERO NO.4ES | HABILITADO Y ARMADO DE ACERO DE REFUERZO DEL NO. 4 FY=4200 KG/CM2 EN ESTRUCTURA | TON | 0.761600 | $16,895.32 | $12,867.48 |
| CONC.H/OF-C=200RN3/4 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 2.500000 | $1,007.95 | $2,519.88 |
| MORTERO CEM-ARE 1:5 | MORTERO CEMENTO ARENA 1:5 | M3 | 0.750000 | $899.87 | $674.90 |
| Suma de Auxiliar | $16,062.25 | ||||
| Concepto | |||||
| EC-003 | CASTILLO K-1 EN ESTRUCTURA, SECCION 15X15 cm DE CONCRETO CON ACERO DE REFUERZO 4 Vs No 3, E No 2 @ 15 cm, fy = 4200 Kg/cm2, INCLUYE: FABRICACION DE CONCRETO f’c=200 Kg/cm2, CON AGREGADO MÁXIMO 3/4" Y ACARREO DE TODOS LOS MATERIALES, VACIADO, VIBRADO Y CURADO CON MEMBRANA, HABILITACION DE ACERO DE REFUERZO, CIMBRA, CIMBRADO, DESCIMBRADO Y TODOS LOS MATERIALES NECESARIOS PARA SU ELABORACION. | M | 10.000000 | $243.25 | $2,432.50 |
| 4070 01 | PLANTILLA CON PEDACERIA DE TABIQUE Y MORTERO CEMENTO-ARENA 1:5, DE 10 cms DE ESPESOR. | M2 | 6.250000 | $49.62 | $310.13 |
| Suma de Concepto | $2,742.63 | ||||
| Costo Directo | $22,213.69 |