| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 50 | RETIRO Y REUBICACION DE POSTES LUMINARIA DEL CAMELLON CENTRAL, INCLUYE MOVIMIENTO DEL POSTE CON GRUA ANCLAJE EN LA NUEVA UBICACION (BASE PARA POSTE) SEGUN PLANO, RETIRO Y TENDIDO DEL CABLEADO, HERRAMIENTA Y MANO DE OBRA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CINTA | CINTA DE PVC AISLANTE SUPER SCOTCH 33 | ML | 0.059380 | $32.00 | $1.90 |
| POLIDUCTO 3/4" | POLIDUCTO NARANJA DE 3/4" | ML | 19.000000 | $2.50 | $47.50 |
| ANCLAS | ANCLAS DE 3/4" | PZA | 4.000000 | $125.00 | $500.00 |
| THW-LS CU 8 AWG | CABLE DE COBRE MONOPOLAR CON AISLAMIENTO THW-LS 90º CALIBRE No. 8 AWG. CALIDAD CONDUMEX O SIMILAR. | ML | 50.000000 | $10.29 | $514.50 |
| TABIQUE ROJO | TABIQUE ROJO | MILL | 0.145000 | $1,278.00 | $185.31 |
| CONCRETO 250 | Concreto premez. f'c=250 kg/cm2 , revenimiento maximo 10 cms +/- 2 cm | m3 | 0.135000 | $864.00 | $116.64 |
| MARCO11 | MARCO Y CONTRAMARCO DE 0.40X0.40 | PIEZA | 1.000000 | $400.00 | $400.00 |
| Suma de Material | $1,765.85 | ||||
| Mano de Obra | |||||
| CUADRILLA NO 84 ( 1 | 1 TEC. ELECTRICISTA + 1 AYTE. DE ELECTRICISTA | jor | 0.326730 | $513.73 | $167.85 |
| CUADRILLA ALBAÑIL-1 | (1 Of. Albanil + 1 Peón) | JOR | 0.592066 | $489.92 | $290.06 |
| Suma de Mano de Obra | $457.92 | ||||
| Equipo | |||||
| AGRUA | CAMION GRUA HIAB 650 | HR | 0.900000 | $325.27 | $292.74 |
| Suma de Equipo | $292.74 | ||||
| Auxiliar | |||||
| CIMBRA | CIMBRA EN CIMENTACION | M2 | 1.080000 | $115.31 | $124.53 |
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1.4 | M3 | 0.096000 | $828.53 | $79.54 |
| CONCRETO 150 KG/CM2 | CONCRETO DE F'C= 150KG/CM2 HECHO EN OBRA AGREGADO MAXIMO 3/4. | M3 | 0.110000 | $829.80 | $91.28 |
| Suma de Auxiliar | $295.35 | ||||
| Costo Directo | $2,811.86 |